| |
|
|
|
|
|
|
•
PoG Skidding System
•
Pohokura Field
Development
•
Wharf Dolphin Access Systems
& Coating
Repairs
• Retractable
Test Stump
Platform
•
Tank & Piping
Modifications
•
Ocean Epoch Deck Extensions
•
Safe Working Platforms
•
Emergency Sea Access
Stair Replacement
•
Fatique Gusset
Installation
•
Diesel Cargo System Refurbishment
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
Technip Oceania
[May 2006 - Sep 2006]
Technip Oceania engaged the services of AME to provide engineering
design, drafting and site personnel during the execution of the
Pohokura field development. AME provided assistance in the following
areas:
Flowline Installation
AME completed engineering design and detailed drafting of the
deflection arch, underoller base seafastenings and developed tie-in
procedures for the DSV, Rocky II.
Jacket and Topsides Installation
AME Engineers formed an integral part of the New Plymouth based
engineering team that reviewed and optimised procedures for the
lift and installation of the Pohokura jacket and topsides.
Self Drilling Piles
After the failure of the primary pile installation methodology,
the New Plymouth engineering team (Technip, Shell, DGS and AME)
developed a sacrificial, direct circulation, under-reaming, sealed
self lubricating drill bit that rotated inside the pile leaving
the pile itself stationary. AME provided key input into the design
of bearings, seals and the lubrication system.
|
|
|
| |
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
MDBM JV
[Sep 2005 - Oct 2005]
As part of the wharf extension project undertaken by McConnell
Dowell Barclay Mowlem Joint Venture (MDBM JV) for Rio Tinto Iron
Ore, an efficient and cost effective solution was required for
accessing the wharf's berthing dolphins in order to seal and coat
flanges and pile sleeves.
AME developed an innovative access system based on inhouse designed
and fabricated aluminium access platfoms. The platforms were designed
to be floated under each dolphin by AME‘s work vessel, then
raised and rigged in position. Utilising this system, significant
time savings were achieved over conventional access systems such
as scaffolding.
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
QED Occtech [Nov
2003 - Mar 2004]
AME was engaged to undertake a variety
of engineering, fabrication and construction tasks associated
with the modification of existing tanks and piping at the Peters
and Brownes Dairy.
Tasks included:
•
Design and drafting of caged ladders
and access platforms in
accordance with Australian standards.
•
Design, fabrication and installation
of specialised mounting plates which allowed water
spray nozzles to be installed within
a tank without the need to enter the tank.
•
Design fabrication and installation
of two inspection hatches.
•
General onsite steelwork and piping
modifications.
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Diamond Offshore [Dec 2003 - Feb
2004]
Due to their 2004 drilling commitments, Diamond Offshore undertook
a program to increase the usable deck area onboard the Ocean Epoch.
AME collaborated with AMASE Inc. of Houston Texas, to design and
draft three new deck extensions. Project Management was performed
in-house by AME, thus ensuring the timely and efficient coordination
of scaffolding, steel fabrication, painting, transportation and
installation activities.
AME personnel carried out preparatory works whilst the rig was under
tow from Bass Strait to perth and subsequently from Perth to Dampier.
Installation of the decks was undertaken over a three week period
(24hrs/7day, 7 days/week), whilst the rig was onsite. As the rig
was operational during the installation phase AME liaised closely
with Diamond Offshore to ensure drilling operations were not interrupted.
|
|
|
|
| |

|
|
|
 |
Aft
Port Deck Extension, being lifted off the helideck ready for installation.
Download
Data Sheet |
|
|
 |
 |
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Jones Lang LaSalle [Aug
2003]
The challenge was to design and install 28 steel
grated platforms (one at each floor level) within two Return Air
Riser Shafts, of the Dumas House Building.
As each shaft measured 1.5m x 7m, the available work space was very
limited and was further restricted by the presence of two circular
air ducts (at either end of the shaft), which varied in diameter
from 350mm to 1100mm.
AME undertook the challenge, designing and installing a modular
platform which provided full unrestricted access to the ducts on
virtually all floors. The platform design incorporated sufficient
flexibility to accommodate the varying diameters of the circular
ducts without the requirement of site fabrication works.
All site assembly was carried out at night, thus ensuring uninter-rupted
use of the building during normal working hours.
|
|
|
|
|
|
 |
|
|
| |
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ICON Engineering [Apr 2003]
AME Pty Ltd was contracted by Icon Engineering
to provide project planning and site supervision services for
the replacement of the emergency sea access stairs onboard the
Ocean Bounty.
The sea access stairs were positioned under the deck of the rig,
and therefore it was not possible to directly use rig cranage
to remove loads. Removal and replacement of the stairs was therefore
carried out using a combination of a remotely positioned winch
and static rigging. The rig crane was used to lower stair components
over the side of the rig, where they were transferred to static
rigging.
Industrial rope access techniques were employed during the demolition
and preliminary steel fit-up phases of the job. Scaffolding was
utilised during the weld out and painting phases.
|
|
|
|
|
|
|
|
 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Diamond Offshore [Mar 2003]
AME was engaged by Diamond Offshore to install lower-hull-diagonal
fatique reinforcement plates onboard the Ocean Epoch.
AME's scope of work encompassed the preparation of installation
work packs, supply of consumables and tools, provision of site
labour, site supervision and preparation of the project MDR (Manfacturers
Data Report).
AME mobilised personnel and equipment form perth and Darwin.
Work entailed steelwork installation at the pontoon level of the
rig. New steel was installed in 16 separate locations.
The installation works were made challenging by arduous environmental
and physical constraints.
|
|
|
|
|
|
|
|
 |
|
|
| |
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ASP Ship Management [Mar
2003]
AME Pty Ltd successfully completed the refurbishment
of various mechanical components associated with HMAS Westralia’s
Diesel Cargo system.
Prior to the commencement of site works, AME worked closely with
the client in order to devise, price and evaluated various refurbish-ment
options.This collaboration proved highly beneficial and allowed
for the optimisation of the client’s allocated schedule and
budget.
AME’s on-site scope of work was composed of two distinct activities
that were run concurrently. The first activity involved the replacement
of three (3) defective 250NB gate valves, located at the bottom
two diesel tanks and the second involved the fabrication, refurbishment
and installation of remote valve actuator components.
|
|
|
|
|
|
|
|
 |
|
|
| |
|
|
|
|
|
|
|
|
|
 |
|
|
|

To view our Data Sheets
you
will require Adobe Acrobat
Reader. If you do not have
the program installed,
please download a free copy. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
 |