Projects 
         

PoG Skidding System

Pohokura Field
   Development


Wharf Dolphin Access    Systems & Coating
   Repairs


Retractable Test Stump
   Platform


Tank & Piping
   Modifications


Ocean Epoch Deck    Extensions

Safe Working Platforms

Emergency Sea Access
   Stair Replacement


Fatique Gusset
   Installation


Diesel Cargo System    Refurbishment

 

PoG Skidding System
Woodside Energy Limited  [Nov 2005 - Dec 2006]

Subsea completions equipment for the Persues over Goodwyn (PoG) campaign was deployed from Diamond Offshore’s MODU, the Ocean Bounty.

AME was engaged by Diamond Offshore and Woodside Energy Limited to design, fabricate and install an equipment handling system that would cater for the various hardware components, and schedule constraints of the PoG project.

AME developed a skidding system that allows equipment to be transferred from under the port hatch of the rig to the centreline of the
moonpool, without utilising the overhead BOP cranes.

To ensure the installation of the system was carried out off critical path temporary steelwork components were also supplied to allow completions operations to commence prior to the installation of the new skidding system.

 

Two stage skidding system
as installed in the moon pool area of the Ocean Bounty.

 Download Data Sheet
   

Pohokura Field Development
Technip Oceania  [May 2006 - Sep 2006]

Technip Oceania engaged the services of AME to provide engineering design, drafting and site personnel during the execution of the Pohokura field development. AME provided assistance in the following areas:

Flowline Installation
AME completed engineering design and detailed drafting of the deflection arch, underoller base seafastenings and developed tie-in procedures for the DSV, Rocky II.

Jacket and Topsides Installation
AME Engineers formed an integral part of the New Plymouth based engineering team that reviewed and optimised procedures for the lift and installation of the Pohokura jacket and topsides.

Self Drilling Piles
After the failure of the primary pile installation methodology, the New Plymouth engineering team (Technip, Shell, DGS and AME) developed a sacrificial, direct circulation, under-reaming, sealed self lubricating drill bit that rotated inside the pile leaving the pile itself stationary. AME provided key input into the design of bearings, seals and the lubrication system.

 

Succcessful lift of the jacket by the Ensco 56, from the
HLV Annegret.

 Download Data Sheet
   

   

Wharf Dolphin Access Systems &
Coating Repairs

MDBM JV  [Sep 2005 - Oct 2005]

As part of the wharf extension project undertaken by McConnell Dowell Barclay Mowlem Joint Venture (MDBM JV) for Rio Tinto Iron Ore, an efficient and cost effective solution was required for accessing the wharf's berthing dolphins in order to seal and coat flanges and pile sleeves.

AME developed an innovative access system based on inhouse designed and fabricated aluminium access platfoms. The platforms were designed to be floated under each dolphin by AME‘s work vessel, then raised and rigged in position. Utilising this system, significant time savings were achieved over conventional access systems such as scaffolding.


Wharf berthing dolphin with accessplatforms, rigged in position.

 Download Data Sheet
   

   

Retractable Test Stump Platform
Diamond Offshore  [Jun - Aug 2004]

Diamond Offshore’s drilling program for the Mutineer-Exeter development required the installation of a retractable test stump to accommodate modifications made to the Ocean Epoch’s BOP.

The location of the platform beneath the cellar deck of the rig presented unique installation difficulties. These where overcome by AME’s early input in the design process and innovative installation methodology.

The platform was fabricated in discrete units which where then passed through a slot cut in the deck, and installed from static rigging. Scaffolding was suspended below decks to create safe working areas for the AME installation team.

Project management was performed in-house by AME, thus ensuring the timely and efficient coordination of all activities, from the design through to final installation.


Rectractable test stump platform ready to be
lowered through the main deck.



 
Download Data Sheet

   

Tank and Piping Modifications
QED Occtech  [Nov 2003 - Mar 2004]

AME was engaged to undertake a variety of engineering, fabrication and construction tasks associated with the modification of existing tanks and piping at the Peters and Brownes Dairy.

Tasks included:

Design and drafting of caged ladders and access platforms in   
  accordance with Australian standards.

Design, fabrication and installation of specialised mounting plates   which allowed water spray nozzles to be installed within
  a tank without the need to enter the tank.

Design fabrication and installation of two inspection hatches.

General onsite steelwork and piping modifications.


Retrofitted tangenial flow inlets to water tank


 Download Data Sheet
 

   
Ocean Epoch Deck Extensions
Diamond Offshore  [Dec 2003 - Feb 2004]

Due to their 2004 drilling commitments, Diamond Offshore undertook a program to increase the usable deck area onboard the Ocean Epoch.

AME collaborated with AMASE Inc. of Houston Texas, to design and draft three new deck extensions. Project Management was performed in-house by AME, thus ensuring the timely and efficient coordination of scaffolding, steel fabrication, painting, transportation and installation activities.

AME personnel carried out preparatory works whilst the rig was under tow from Bass Strait to perth and subsequently from Perth to Dampier. Installation of the decks was undertaken over a three week period (24hrs/7day, 7 days/week), whilst the rig was onsite. As the rig was operational during the installation phase AME liaised closely with Diamond Offshore to ensure drilling operations were not interrupted.


Aft Port Deck Extension, being lifted off the helideck ready for installation.


 
Download Data Sheet

   
Safe Working Platforms
Jones Lang LaSalle  [Aug 2003]

The challenge was to design and install 28 steel grated platforms (one at each floor level) within two Return Air Riser Shafts, of the Dumas House Building.

As each shaft measured 1.5m x 7m, the available work space was very limited and was further restricted by the presence of two circular air ducts (at either end of the shaft), which varied in diameter from 350mm to 1100mm.

AME undertook the challenge, designing and installing a modular platform which provided full unrestricted access to the ducts on virtually all floors. The platform design incorporated sufficient flexibility to accommodate the varying diameters of the circular ducts without the requirement of site fabrication works.

All site assembly was carried out at night, thus ensuring uninter-rupted use of the building during normal working hours.



Dumas House Building


 
Download Data Sheet

   

Emergency Sea Access Stair Replacement
ICON Engineering  [Apr 2003]

AME Pty Ltd was contracted by Icon Engineering to provide project planning and site supervision services for the replacement of the emergency sea access stairs onboard the Ocean Bounty.

The sea access stairs were positioned under the deck of the rig, and therefore it was not possible to directly use rig cranage to remove loads. Removal and replacement of the stairs was therefore carried out using a combination of a remotely positioned winch and static rigging. The rig crane was used to lower stair components over the side of the rig, where they were transferred to static rigging.

Industrial rope access techniques were employed during the demolition and preliminary steel fit-up phases of the job. Scaffolding was utilised during the weld out and painting phases.


Sea Access Stairs during weld-out of new.

 
Download Data Sheet

   

Fatique Gusset Installation
Diamond Offshore  [Mar 2003]

AME was engaged by Diamond Offshore to install lower-hull-diagonal fatique reinforcement plates onboard the Ocean Epoch.

AME's scope of work encompassed the preparation of installation work packs, supply of consumables and tools, provision of site labour, site supervision and preparation of the project MDR (Manfacturers Data Report).

AME mobilised personnel and equipment form perth and Darwin.

Work entailed steelwork installation at the pontoon level of the rig. New steel was installed in 16 separate locations.

The installation works were made challenging by arduous environmental and physical constraints.


Welding-out 180kg gusset
on rig column SC3.



 
Download Data Sheet

   
Diesel Cargo System Refurbishment
ASP Ship Management  [Mar 2003]

AME Pty Ltd successfully completed the refurbishment of various mechanical components associated with HMAS Westralia’s Diesel Cargo system.

Prior to the commencement of site works, AME worked closely with the client in order to devise, price and evaluated various refurbish-ment options.This collaboration proved highly beneficial and allowed for the optimisation of the client’s allocated schedule and budget.

AME’s on-site scope of work was composed of two distinct activities that were run concurrently. The first activity involved the replacement of three (3) defective 250NB gate valves, located at the bottom two diesel tanks and the second involved the fabrication, refurbishment and installation of remote valve actuator components.



Replenishment Ship HMAS Westralia docked at Garden Island


 
Download Data Sheet
Downlaod Acrobat Reader

To view our Data Sheets you
will require Adobe Acrobat
Reader. If you do not have
the program installed,
please download a free copy.
 
     
         
ISO 9001 Certificate of Approval
       
   
 
Design by Brand&Profile
Top of page
© 2007 AME Pty Ltd